Weeks 8 to 12

Week 8 the new access road is being put in to “The Orchard”

Week 9 piling has now been completed to the social enterprise centre

Week 10 More drains

Week 11 Making ready for pouring the concrete. Did you know that concrete never sets! It reaches a crushing strength.

Week 12 Steeling the ring beam to support the frame of the building.